SNYDER – The Snyder Independent School District (SISD) engineer is drawing up plans to replace a gas line that runs between the star gym and the indoor facility.Clay Cade, SISD director of operations, said he had an estimate of $127,000 to dig up and replace the 60 foot line. He said the school would have to make another contract to replace the concrete between the two buildings. He said the cost of the project requires the district to design plans and open the contract up to public contractors.Cade said the project should be done in October and that it would ...